Ventura - S Mills Road and E Main Street - Pipeline Replacement

There is a pipeline enhancement project in the City of Ventura. If you have any questions, please contact us:

Project Call Number:  Olga Quinones, (805) 551-9027
Project E/mail: ProjectInfo@socalgas.com

Project Status 10/21: 

This week construction conducted around the clock activities and road closures starting on October 16th through the 18th on S. Mills Road and Telegraph Road. As well as E. Main Street and Telephone Road. The project is approximately at 90% complete.

Project Details:

  • Replacement Segment Start and End Location, Nearest Cross Streets: Telegraph Road and S Mills Road.
  • Projected Start Date: June 2019
  • Projected End Date: December 2019
  • Traffic Impacts: To minimize the impact to the community, work is planned for nights starting at 10 p.m. to 6 a.m.

People passing by a work sites may see an excavation, equipment, vehicles and traffic control signage. The community may also hear some work-related noise and notice an occasional natural gas odor.